Current cost
$128.8 million
As published 24 March 2026
Completion
1 September 2028
Most recently published
Re-baselines
0
Times the cost or completion date changed
- Proposed
- Funded (current)
- Under way
- Delivered
Stage: Funded of Delivered
What has changed
Nothing yet. Only one cost or completion date has ever been published for this project, so there is no change to report. That is not the same as being on track.
The ledger
| Stated | Cost | Completion | Status | What was said |
|---|---|---|---|---|
| $128.8 million | Funded, not started | Approved in principle by councillors. A design and construction estimate of $128.8 million for Wyndham's third public aquatic facility, on six hectares of council land near Riverdale Town Centre. A 10-lane 25-metre lap pool, a separate 25-metre program pool, a wellness area, indoor and outdoor water play and a gym. Construction projected to start around September 2028. Wyndham City Council |
Who to contact
No contact officer is publicly named. Wyndham City Council is the responsible body.