Wyndham bus network upgrades
DeliveredDepartment of Transport and Planning
$100 million
As published 15 September 2026
Down $0 on the first published figure of $100 million
- Tarneit
- Truganina
- Mambourin
- Wyndham Vale
What is being built in Wyndham, what it costs, and whether the cost or the completion date has changed since it was promised.
Projects with a public commitment behind them. Where a cost or a completion date has been stated more than once, the card shows the change.
Department of Transport and Planning
$100 million
As published 15 September 2026
Down $0 on the first published figure of $100 million
Victorian Government, Level Crossing Removal Project
$200 million
As published 13 September 2026
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
$250 million
As published 1 June 2026
Down $0 on the first published figure of $250 million
Victorian Health Building Authority with Mercy Health
$280 million
As published 1 May 2026
Up $44 million on the first published figure of $236 million
Wyndham City Council
$128.8 million
As published 24 March 2026
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Victorian School Building Authority
Never publicly costed
Victorian School Building Authority has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Victorian and Australian Governments, Rail Projects Victoria
$12 billion
As published 1 January 2026
Down $0 on the first published figure of $12 billion
Court Services Victoria
$274 million
As published 10 November 2025
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Department of Energy, Environment and Climate Action, with Wyndham City Council
Never publicly costed
Department of Energy, Environment and Climate Action, with Wyndham City Council has not published this
Level Crossing Removal Project
Never publicly costed
Level Crossing Removal Project has not published this
These are the 16 priority projects in Wyndham City Council’s A Way Forward for Wyndham campaign for the Victorian state election on 28 November 2026. They are requests, not commitments. No cost figures are published on the campaign page, so none are shown here.
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Wyndham City Council
Never publicly costed
Wyndham City Council has not published this
Suburban Rail Loop Authority
Never publicly costed
Suburban Rail Loop Authority has not published this