Current cost
$274 million
As published 10 November 2025
Completion
10 November 2025
Most recently published
Re-baselines
0
Times the cost or completion date changed
- Proposed
- Funded
- Under way
- Delivered (current)
Stage: Delivered of Delivered
What has changed
Nothing yet. Only one cost or completion date has ever been published for this project, so there is no change to report. That is not the same as being on track.
The ledger
| Stated | Cost | Completion | Status | What was said |
|---|---|---|---|---|
| $274 million | Delivered | Opened to the public. Victoria's largest court complex outside the Melbourne central business district: 13 courtrooms, four hearing rooms, three mediation suites. Houses the Magistrates' Court, the Children's Court and the Victorian Civil and Administrative Tribunal (VCAT). The Werribee Magistrates' Court closed permanently on 31 October 2025. Court Services Victoria |
Who to contact
Court Services Victoria
Sources
- 1. Wyndham Law Courts development — Court Services VictoriaChecked 7 October 2026 · all rights reserved, linked not reproduced