Current cost
$280 million
As published 1 May 2026
Completion
31 December 2026
Most recently published
Re-baselines
2
Times the cost or completion date changed
- Proposed
- Funded
- Under way (current)
- Delivered
Stage: Under way of Delivered
What has changed
First publicly costed at $236 million on 3 May 2022. Most recently $280 million — an increase of $44 million, or 1.19× the original figure.
The ledger
| Stated | Cost | Completion | Status | What was said |
|---|---|---|---|---|
| $236 million | Not published | Funded, not started | 2022-23 Victorian Budget total estimated cost, for a program covering both Werribee Mercy and Casey Hospital emergency departments. Victorian Health Building Authority | |
| $280 million | Not published | Under way | The 2024-25 Victorian Budget raised the program total. Main works commenced in August 2024. Victorian Health Building Authority | |
| $280 million | Under way | The 2026-27 Victorian Budget allocated $95 million toward opening the upgraded emergency department. On track for completion in 2026. Doubles emergency department capacity, adding about 25,000 presentations a year, four resuscitation bays, 16 short-stay beds and 36 emergency care cubicles. Victorian Health Building Authority |
Who to contact
Victorian Health Building Authority
Sources
- 1. Werribee Mercy Hospital emergency department expansion — Victorian Health Building AuthorityChecked 7 October 2026 · all rights reserved, linked not reproduced
- 2. Major Projects Performance Reporting 2023 — Victorian Auditor-General's OfficeChecked 7 October 2026 · all rights reserved, linked not reproduced