Current cost
Never publicly costed
Wyndham City Council has not published this
Completion
1 August 2026
Most recently published
Re-baselines
0
Times the cost or completion date changed
- Proposed
- Funded
- Under way
- Delivered (current)
Stage: Delivered of Delivered
What has changed
Nothing yet. Only one cost or completion date has ever been published for this project, so there is no change to report. That is not the same as being on track.
The ledger
| Stated | Cost | Completion | Status | What was said |
|---|---|---|---|---|
| Never publicly costed | Delivered | Complete. Double the lanes, new traffic signals and improved cycling connections. No cost figure published. Wyndham City Council |
Who to contact
Wyndham City Council, 1300 023 411
Sources
- 1. Tarneit Road and Leakes Road intersection upgrade complete — Wyndham City CouncilChecked 7 October 2026 · all rights reserved, linked not reproduced